The director of cost management for Odessa Company uses a control chart
Managerial AccountingBudgeting & Variances
The textbook question
Required information
EX 10-28 (Algo) Cost Variance Investigation (LO 10-4)
The director of cost management for Odessa Company uses a statistical control chart to help management determine when to investigate variances. The critical value is 1 standard deviation. The company incurred the following direct-labor efficiency variances during the first six months of the current year.
| Month | Variance |
|---|---|
| January | $420 F |
| February | 970 U |
| March | 870 U |
| April | 1,070 U |
| May | 1,220 U |
| June | 1,840 U |
The standard direct-labor cost during each of these months was $36,000. The controller has estimated that the firm's monthly direct-labor variances have a standard deviation of $1,120.
EX 10-28 (Algo) Part 2: Which variances will be investigated?
Required:
2-a. Determine the cutoff value for investigation if the controller's rule of thumb is to investigate all variances equal to or greater than 5 percent of standard cost.
2-b. Based on the cutoff value, which month will have its direct-labor efficiency variance investigated?
Below is the Accuity problem: the same method with different numbers. We solve ours, so work through it and you'll know how to solve yours.
The Accuity problem
Accuity's cost-management lead tracks variances on a statistical control chart and treats one standard deviation as the critical value. Here are the direct-labor efficiency variances for the first six months of the year:
| Month | Variance |
|---|---|
| January | $550 F |
| February | 650 U |
| March | 800 U |
| April | 2,000 U |
| May | 1,400 U |
| June | 950 U |
Standard direct-labor cost was $38,000 in each of those months. The controller puts the standard deviation of monthly direct-labor variances at $1,000.
- The controller's rule of thumb is to look into any variance that is at least 5% of standard cost. What is the cutoff for investigation?
- Using that cutoff, which month's direct-labor efficiency variance will be investigated?
An Accuity original. We write our own version of each problem and solve it from scratch, so you learn the method rather than copying an answer.
Video solution
Covers the full step-by-step solution below, start to finish.

Solved by
Jake Glidden, CPA, MSA
Founder of Accuity
Jake started Accuity while studying accounting at UCF and has worked with hundreds of students in introductory and upper-level accounting classes. Accuity solutions are checked against the textbook before they're published.
Certified Public Accountant (CPA) · B.S.B.A. in Accounting, UCF · M.S. in Accounting, UCF
More about Accuity →Step-by-step solution
The same steps the video works through, written out.
This problem tests variance investigation: deciding which variances are big enough to be worth a manager's time. Small variances happen by chance every month, so companies set a cutoff and look only at variances that reach it. This question uses a percentage-of-standard-cost rule of thumb.
Requirement 1 — The cutoff
Cutoff = 5% × Standard direct-labor cost = 5% × $38,000 = $1,900
Any variance of $1,900 or more gets investigated, whether it is favorable or unfavorable. Size is what matters, not direction.
Requirement 2 — Which month is investigated?
Compare each month's variance with $1,900:
| Month | Variance | At least $1,900? |
|---|---|---|
| January | $550 F | No |
| February | 650 U | No |
| March | 800 U | No |
| April | 2,000 U | Yes |
| May | 1,400 U | No |
| June | 950 U | No |
Only April's variance ($2,000 U) is investigated.
How this compares with the control chart
The setup also gives a statistical rule: a critical value of one standard deviation, or $1,000. Under that rule, April ($2,000 U) and May ($1,400 U) would both exceed the limit. The 5% rule of thumb sets a higher bar here, so it flags only April. Read the requirement carefully to see which rule it asks for. This one asks only for the 5% rule.
A pattern can matter too: five unfavorable months in a row suggest labor efficiency is drifting, even though only one month crosses the cutoff.
Where students go wrong
- Using the standard deviation as the cutoff. The requirement asks for 5% of standard cost, $1,900, not $1,000.
- Ignoring favorable variances. A large favorable variance would also be investigated; January's $550 F is simply too small.
- Taking 5% of the variance instead of 5% of the $38,000 standard cost.
More Budgeting & Variances problems
- New Jersey Valve Company manufactured 9,000 units during JanuaryThis problem tests your ability to calculate standard production costs and analyze material and labor variances. You'll compute price, quantity, rate, and efficiency variances to understand production performance against standards.
- GreenThumb Organic Fertilizer Company plans to sell 250,000 units in JulyThis problem tests your ability to forecast production needs based on sales growth and ending inventory targets, then calculate raw-material purchase costs. You'll work through multi-month production budgets and inventory management policies to determine both required units and purchase expenses.
- Bodin Company budgets on an annual basis: production and raw materialTests production budgeting and raw material purchase calculations using inventory flow equations. Solutions require computing units to manufacture from sales and ending inventory targets, then determining material purchases from production needs and inventory levels.
- The controller for Rainbow Children's Hospital, located in Munich, GermanyThis problem tests your ability to build flexible budgets using both formula and columnar formats for a hospital's variable and fixed electricity expenses. You'll calculate the budgeted variable cost per patient-day and apply it across different activity levels.
- Crystal Glassware Company standards and flexible-budget dataThis problem tests computation of four overhead variances using standard formulas: variable spending and efficiency variances, and fixed budget and volume variances. Solutions require comparing actual overhead costs and labor hours against flexible-budget standards.
Got a different wording of this problem?
Assignments vary by school and semester. Share the version you were given and we'll add it so other students can find this solution.