WMEJ is an independent television station run by a major state university. The station's broadcast hours vary during the year depending on whether the university is in session. The station's production-crew and supervisory costs are as follows for July and September.

Managerial AccountingCost Behavior & CVP

What the textbook asks

Cost ItemCost BehaviorCost AmountBroadcast Hours during Month
Production crewVariable
July$ 4,560380
September7,680640
Supervisory employeesFixed
July4,300380
September4,300640

Required:
1. Compute the cost per broadcast hour during July and September for each of these cost items.
2. What will be the total amount incurred for each of these costs during December, when the station's activity will be 410 broadcast hours?
3. What will be the cost per broadcast hour in December for each of the cost items?

Note: Round your answers to 2 decimal places.

Below is the Accuity problem: the same method with different numbers. We solve ours, so work through it and you'll know how to solve yours.

The Accuity problem

Accuity runs a learning center owned by a large state university. How many hours the center teaches each month rises and falls with the university's academic calendar. Its teaching-staff and supervisor costs for August and September were:

Cost itemCost behaviorMonthCostTeaching hours
Teaching staffVariableAugust$2,400300
Teaching staffVariableSeptember2,720340
SupervisorsFixedAugust4,000300
SupervisorsFixedSeptember4,000340

Round per-hour amounts to the nearest cent.

  1. For each cost item, find the cost per teaching hour in August and in September.
  2. The center expects to teach 410 hours in December. What total cost should it expect for each cost item that month?
  3. For each cost item, what will the cost per teaching hour be in December?

An Accuity original. We write our own version of each problem and solve it from scratch, so you learn the method rather than copying an answer.

Video solution

Covers the full step-by-step solution below, start to finish.

Jake Glidden, CPA, MSA

Solved by

Jake Glidden, CPA, MSA

Founder of Accuity

Jake started Accuity while studying accounting at UCF and has worked with hundreds of students in introductory and upper-level accounting classes. Accuity solutions are checked against the textbook before they're published.

Certified Public Accountant (CPA) · B.S.B.A. in Accounting, UCF · M.S. in Accounting, UCF

More about Accuity →

Step-by-step solution

The same steps the video works through, written out.

This problem tests how variable and fixed costs behave in total and per unit as activity changes. The activity measure is teaching hours.

The rule, side by side:

Total costCost per hour
Variable costChanges with hoursStays the same
Fixed costStays the sameChanges (falls as hours rise)

Requirement 1 — Cost per teaching hour, August and September

Cost itemAugustSeptember
Teaching staff$2,400 ÷ 300 = $8.00$2,720 ÷ 340 = $8.00
Supervisors$4,000 ÷ 300 = $13.33$4,000 ÷ 340 = $11.76

The teaching-staff cost is $8.00 per hour in both months, which confirms it is variable. The supervisor cost per hour drops from $13.33 to $11.76 because the same $4,000 is spread over more hours.

Requirement 2 — Total cost in December (410 hours)

Teaching staff (variable): use the per-hour rate.

$8.00 × 410 = $3,280

Supervisors (fixed): the total doesn't change with hours.

$4,000

Requirement 3 — Cost per teaching hour in December

Teaching staff: still $8.00 per hour ($3,280 ÷ 410).

Supervisors: $4,000 ÷ 410 = $9.76 per hour

Summary

Cost itemTotal in DecemberPer hour in December
Teaching staff$3,280$8.00
Supervisors$4,000$9.76

Why the per-hour fixed cost is risky to use

The supervisor cost per hour has now been $13.33, $11.76 and $9.76, three different numbers for the same $4,000 of cost. A fixed cost per unit is only true at the volume it was computed for. That's why managers budget fixed costs as a monthly total and variable costs as a rate per unit of activity.

Where students go wrong

  • Predicting a fixed cost with a per-hour rate. Multiplying $13.33 (or $11.76) by 410 hours gives a December supervisor cost of over $4,800. A fixed cost stays $4,000 in total; only the per-hour figure changes.
  • Treating the variable cost per hour as changing. The teaching-staff rate is $8.00 at 300, 340 and 410 hours. The total is what moves.
  • Rounding too early. Divide the full $4,000 by each month's hours and round only the final per-hour answer.

More Cost Behavior & CVP problems

Got a different wording of this problem?

Assignments vary by school and semester. Share the version you were given and we'll add it so other students can find this solution.

Studying Cost Behavior & CVP for a class?

Accuity courses map to your actual syllabus — video lessons, exam-style practice, and walkthroughs for the problems you're assigned.

Ace your accounting classes.

Textbook questions are for reference. We show a textbook's question only so you can find the problem you were assigned. We don't solve textbook questions: every solution and video on this site works through our own Accuity problem, written to teach the same method with different numbers.

Educational use. Accuity problems are original teaching material — we write our own version of each problem and solve it on video so you learn the method. Don't submit our work as your own; that violates your school's academic integrity policy. If you believe content here infringes your rights, file a DMCA notice.