Work-in-process inventory is composed of

Managerial AccountingCost Behavior & CVP

The textbook question

Work-in-process inventory is composed of:

  • direct labor and manufacturing overhead.
  • direct material and direct labor.
  • direct material, direct labor, and manufacturing overhead.
  • direct material and manufacturing overhead.
  • direct material only.

Below is the Accuity problem: the same method with different numbers. We solve ours, so work through it and you'll know how to solve yours.

The Accuity problem

Which costs make up the balance in a manufacturer's work-in-process inventory?

A) Direct labor and manufacturing overhead
B) Direct materials and direct labor
C) Direct materials, direct labor and manufacturing overhead
D) Direct materials and manufacturing overhead

An Accuity original. We write our own version of each problem and solve it from scratch, so you learn the method rather than copying an answer.

Video solution

Covers the full step-by-step solution below, start to finish.

Jake Glidden, CPA, MSA

Solved by

Jake Glidden, CPA, MSA

Founder of Accuity

Jake started Accuity while studying accounting at UCF and has worked with hundreds of students in introductory and upper-level accounting classes. Accuity solutions are checked against the textbook before they're published.

Certified Public Accountant (CPA) · B.S.B.A. in Accounting, UCF · M.S. in Accounting, UCF

More about Accuity →

Step-by-step solution

The same steps the video works through, written out.

Answer: C) Direct materials, direct labor and manufacturing overhead

This question tests what goes into work-in-process inventory, the account that holds the cost of units started but not yet finished.

The rule

All three manufacturing cost elements flow into work in process:

Cost elementHow it enters work in process
Direct materialsMoved from raw materials when issued to production
Direct laborCharged as workers make the product
Manufacturing overheadApplied using a predetermined overhead rate

In journal-entry form, work in process is debited for all three, and when units are finished their full cost moves on to finished goods.

Why the other choices are wrong

  • A) leaves out direct materials, usually the largest cost in a unit.
  • B) is prime cost. It leaves out overhead, which is a product cost and must be inventoried.
  • D) leaves out direct labor.

Each wrong choice is missing one of the three, so the test is simply remembering that product cost needs all three.

Where students go wrong

Picking B because overhead "isn't traceable." Overhead can't be traced to units directly, but it is still a product cost. That's why it is applied to work in process with a rate instead of being expensed.

More Cost Behavior & CVP problems

Got a different wording of this problem?

Assignments vary by school and semester. Share the version you were given and we'll add it so other students can find this solution.

Studying Cost Behavior & CVP for a class?

Accuity courses map to your actual syllabus — video lessons, exam-style practice, and walkthroughs for the problems you're assigned.

Ace your accounting classes.

Textbook questions are for reference. We show a textbook's question only so you can find the problem you were assigned. We don't solve textbook questions: every solution and video on this site works through our own Accuity problem, written to teach the same method with different numbers.

Educational use. Accuity problems are original teaching material — we write our own version of each problem and solve it on video so you learn the method. Don't submit our work as your own; that violates your school's academic integrity policy. If you believe content here infringes your rights, file a DMCA notice.