Project requiring construction expenses through year 2: IRR and NPV
Business FinanceCapital Budgeting
The question
The following project requires construction expenses through year 2, followed by cash inflows from year 3 through 8. If the required rate of return is 13%, is the project acceptable? Use IRR and NPV.
| Year | Cash Flows |
|---|---|
| 0 | -$765,000 |
| 1 | -600,000 |
| 2 | -550,000 |
| 3 | 150,000 |
| 4 | 450,000 |
| 5-8 | 850,000 |
Below is the Accuity problem: the same method with different numbers. We solve ours, so work through it and you'll know how to solve yours.
The Accuity problem
A BlueWave Construction project has construction costs through year 2, then cash inflows from year 3 through year 8. The required rate of return is 14%.
| Year | Cash Flows |
|---|---|
| 0 | (800,000) |
| 1 | (650,000) |
| 2 | (580,000) |
| 3 | 160,000 |
| 4 | 480,000 |
| 5-8 | 900,000 |
- Using IRR and NPV, is the project acceptable?
An Accuity original. We write our own version of each problem and solve it from scratch, so you learn the method rather than copying an answer.
Video solution
Covers the full step-by-step solution below, start to finish.

Solved by
Jake Glidden, CPA, MSA
Founder of Accuity
Jake started Accuity while studying accounting at UCF and has worked with hundreds of students in introductory and upper-level accounting classes. Accuity solutions are checked against the textbook before they're published.
Certified Public Accountant (CPA) · B.S.B.A. in Accounting, UCF · M.S. in Accounting, UCF
More about Accuity →Step-by-step solution
The same steps the video works through, written out.
This problem tests NPV and IRR for a project with several years of outflows before any inflows. The cash flows still change sign only once (three negatives, then positives), so the project is conventional and has a single IRR.
Enter the cash flows (HP 10BII+)
[shift] [C ALL],1 [shift] [P/YR]800000 [+/-] [CFj]650000 [+/-] [CFj]580000 [+/-] [CFj]160000 [CFj]480000 [CFj]900000 [CFj],4 [shift] [Nj](years 5 through 8)
NPV at 14%
14 [I/YR], [shift] [NPV] → 128,363.80
| Year | Cash flow | PV at 14% |
|---|---|---|
| 0 | (800,000) | (800,000.00) |
| 1 | (650,000) | (570,175.44) |
| 2 | (580,000) | (446,291.17) |
| 3 | 160,000 | 107,995.44 |
| 4 | 480,000 | 284,198.53 |
| 5 | 900,000 | 467,431.80 |
| 6 | 900,000 | 410,027.89 |
| 7 | 900,000 | 359,673.59 |
| 8 | 900,000 | 315,503.15 |
| NPV | 128,363.80 |
The construction costs are worth $1,816,466.61 in today's dollars, and the inflows are worth $1,944,830.40, a margin of about $128,364.
IRR
[shift] [IRR/YR] → 15.57
At 15.57% the inflows exactly offset the outflows, so NPV = 0.
Decision
| Method | Result | Hurdle | Decision |
|---|---|---|---|
| NPV | $128,363.80 | > $0 | Accept |
| IRR | 15.57% | > 14% | Accept |
Answer: the project is acceptable. NPV is about $128,363.80 (positive) and IRR is about 15.57% (above the 14% required return).
Why the two methods agree
For a single, independent project with conventional cash flows, NPV and IRR always give the same accept/reject decision: if the IRR is above the required return, discounting at the required return must leave a positive NPV. The margin here is thin (about 1.6 percentage points), so the project is sensitive to delays or cost overruns during construction.
Mistakes to avoid
- Entering the year 1 and year 2 construction costs as positive numbers.
- Entering 900,000 once instead of setting Nj = 4, which drops three years of inflows.
- Treating the row "5-8" as a single year.
More Capital Budgeting problems
- Lopez Industries projects A and B: MIRR compared with NPVModified internal rate of return for two mutually exclusive projects, compounding inflows at the required return, and a check of whether MIRR agrees with NPV.
- Neagle Corporation imposes a payback cutoff of 2.5 years: payback vs. NPVApplies a payback cutoff to two projects, then computes each project's NPV and shows where payback and NPV disagree, including the mutually exclusive choice.
- Consider the following cash flows that switch signs: IRR or NPV at 11%Non-conventional cash flows that change sign several times: computes the IRR, explains why IRR can be unreliable here, and confirms the decision with NPV and MIRR.
- Nonlinear Dynamics, Inc. must decide between two game projects: EAAChooses between two mutually exclusive projects with different lives and different risk-adjusted rates by converting each NPV into an equivalent annual annuity.
- Suppose your firm is choosing between two exclusive projects: PI vs. NPVRanks two mutually exclusive projects of different size by profitability index and by NPV, then explains why the ratio and the dollar measure disagree.
- Franchise investment in Lazy Moon Pizza: 15-year NPV and IRRFranchise investment with land, building, equipment, working capital and a franchise fee: annual cash flow from monthly figures, terminal value of land and building, NPV and IRR.
Got a different wording of this problem?
Assignments vary by school and semester. Share the version you were given and we'll add it so other students can find this solution.
Studying Capital Budgeting for a class?
Accuity courses map to your actual syllabus — video lessons, exam-style practice, and walkthroughs for the problems you're assigned.