By purchasing training software for $7,000, you can eliminate other training costs of $3,400 each year for the next 10 years. What is the IRR of the software?
Business FinanceCapital Budgeting
What the question asks
a. 50.45%
b. 46.55%
c. 47.58%
d. 48.25%
e. 52.13%
Below is the Accuity problem: the same method with different numbers. We solve ours, so work through it and you'll know how to solve yours.
The Accuity problem
Accuity can spend $8,000 on training software that would eliminate $3,750 of other training costs every year for the next 10 years.
- What is the internal rate of return (IRR) on the software?
An Accuity original. We write our own version of each problem and solve it from scratch, so you learn the method rather than copying an answer.
Video solution
Covers the full step-by-step solution below, start to finish.

Solved by
Jake Glidden, CPA, MSA
Founder of Accuity
Jake started Accuity while studying accounting at UCF and has worked with hundreds of students in introductory and upper-level accounting classes. Accuity solutions are checked against the textbook before they're published.
Certified Public Accountant (CPA) · B.S.B.A. in Accounting, UCF · M.S. in Accounting, UCF
More about Accuity →Step-by-step solution
The same steps the video works through, written out.
This question tests the internal rate of return (IRR) for an investment whose payoff is a level annual saving. Training costs that disappear are cash inflows, so the software is an $8,000 outflow today followed by ten inflows of $3,750.
The rule
IRR is the discount rate at which NPV = 0:
$8,000 = $3,750 × PVIFA(IRR, 10)
PVIFA = $8,000 ÷ $3,750 = 2.13333
HP 10BII+ keystrokes
1 [shift] [P/YR]10 [N]8000 [+/-] [PV]3750 [PMT]0 [FV][I/YR]→ 45.79
Cash flow method (same answer): 8000 [+/-] [CFj], 3750 [CFj] 10 [shift] [Nj], [shift] [IRR/YR].
Check the answer
| Rate | PVIFA(rate, 10) | PV of $3,750 a year |
|---|---|---|
| 40% | 2.41357 | $9,051 |
| 45.79% | 2.13333 | $8,000 |
| 50% | 1.96532 | $7,370 |
At 45.79% the savings are worth exactly the $8,000 cost.
Answer: the IRR is about 45.79%.
What it means
The software pays for itself in a little over two years ($8,000 ÷ $3,750 = 2.13 years) and keeps saving money for about eight more. Any realistic required return is far below 45.79%, so the purchase should be accepted.
Why there is only one IRR
The cash flows change sign only once (one outflow, then all inflows). A conventional pattern like this has exactly one IRR, so the IRR rule gives a clear accept or reject signal. Multiple IRRs only become a risk when the cash flows switch signs more than once.
Mistakes to avoid
- Forgetting the minus sign on the $8,000, which makes the calculator report an error.
- Leaving an old FV or P/YR setting in the calculator.
- Dividing the annual saving by the cost ($3,750 ÷ $8,000 = 46.9%). That is the first-year return, not the IRR, because it ignores that the savings stop after 10 years.
More Capital Budgeting problems
- Lopez Industries projects A and B: MIRR compared with NPVModified internal rate of return for two mutually exclusive projects, compounding inflows at the required return, and a check of whether MIRR agrees with NPV.
- Neagle Corporation imposes a payback cutoff of 2.5 years: payback vs. NPVApplies a payback cutoff to two projects, then computes each project's NPV and shows where payback and NPV disagree, including the mutually exclusive choice.
- Project requiring construction expenses through year 2: IRR and NPVIRR and NPV for a project with three years of construction outflows before eight years of inflows, using grouped cash flows on the HP 10BII+.
- Consider the following cash flows that switch signs: IRR or NPV at 11%Non-conventional cash flows that change sign several times: computes the IRR, explains why IRR can be unreliable here, and confirms the decision with NPV and MIRR.
- Nonlinear Dynamics, Inc. must decide between two game projects: EAAChooses between two mutually exclusive projects with different lives and different risk-adjusted rates by converting each NPV into an equivalent annual annuity.
- Suppose your firm is choosing between two exclusive projects: PI vs. NPVRanks two mutually exclusive projects of different size by profitability index and by NPV, then explains why the ratio and the dollar measure disagree.
Got a different wording of this problem?
Assignments vary by school and semester. Share the version you were given and we'll add it so other students can find this solution.
Studying Capital Budgeting for a class?
Accuity courses map to your actual syllabus — video lessons, exam-style practice, and walkthroughs for the problems you're assigned.