PrimeTech Manufacturing automation equipment with sunk costs: IRR and NPV
Business FinanceCapital Budgeting
The question
MegaStuff Manufacturing, Inc. is thinking about buying some computer equipment to partially automate several of the firm's production lines. The equipment is recommended by a manufacturing consultant, who was hired by MegaStuff to study their production processes earlier this year. MegaStuff paid the consultant $25,000 for the analysis. An additional $50,000 has already been spent on employee training sessions, to ease the transition if the equipment is purchased. The computer equipment will cost $550,000. Delivery and setup costs will cost an additional $25,000. In addition, $15,000 in net working capital will be required at installation. The equipment will have a 5 year class life and will be depreciated using simplified straight line. MegaStuff has a tax rate of 21% and a cost of capital of 14%.
Currently, the firm's annual operating expenses total $640,000. The new equipment will decrease the firm's operating expenses to $400,000 per year.
S'pose MegaStuff decides to keep the equipment for 8 years and sell it for $40,000 at the end of year 8. What are the project's IRR and NPV?
Below is the Accuity problem: the same method with different numbers. We solve ours, so work through it and you'll know how to solve yours.
The Accuity problem
PrimeTech Manufacturing Inc. is considering $600,000 of equipment to automate its production lines. A consultant, paid $30,000, recommended the equipment, and PrimeTech has already spent $50,000 on training sessions before deciding whether to buy. If the company buys the equipment, it will spend $28,000 on shipping and need $18,000 of working capital. The equipment has a 5-year life and is depreciated straight-line. PrimeTech's tax rate is 21% and its cost of capital is 15%.
| Annual operating expenses | Amount |
|---|---|
| Current | $680,000 |
| Projected with the new equipment | $420,000 |
- If PrimeTech keeps the equipment for 9 years and sells it for $45,000 at the end, what are the project's IRR and NPV?
An Accuity original. We write our own version of each problem and solve it from scratch, so you learn the method rather than copying an answer.
Video solution
Covers the full step-by-step solution below, start to finish.

Solved by
Jake Glidden, CPA, MSA
Founder of Accuity
Jake started Accuity while studying accounting at UCF and has worked with hundreds of students in introductory and upper-level accounting classes. Accuity solutions are checked against the textbook before they're published.
Certified Public Accountant (CPA) · B.S.B.A. in Accounting, UCF · M.S. in Accounting, UCF
More about Accuity →Step-by-step solution
The same steps the video works through, written out.
This problem tests which costs belong in a capital budgeting analysis and what happens when an asset is kept longer than its depreciation life.
Sunk costs are ignored
The $30,000 consultant fee and the $50,000 of training have already been spent and cannot be recovered whether or not PrimeTech buys the equipment. They are sunk costs and are left out.
Initial outlay (year 0)
| Item | Amount |
|---|---|
| Equipment | $600,000 |
| Shipping | 28,000 |
| Depreciable base | 628,000 |
| Working capital | 18,000 |
| Initial outlay | $646,000 |
Annual cash flows
Savings = 680,000 − 420,000 = $260,000 per year. Depreciation = 628,000 / 5 = $125,600 for years 1-5, then $0.
| Years 1-5 | Years 6-9 | |
|---|---|---|
| Operating savings | $260,000 | $260,000 |
| Depreciation | (125,600) | 0 |
| Earnings before tax | 134,400 | 260,000 |
| Taxes (21%) | (28,224) | (54,600) |
| Net income | 106,176 | 205,400 |
| Add back depreciation | 125,600 | 0 |
| Operating cash flow | $231,776 | $205,400 |
Cash flow falls by $26,376 after year 5 because the depreciation tax shield (21% × 125,600) ends.
Terminal cash flow (year 9)
The equipment is fully depreciated, so the entire $45,000 is a taxable gain.
| Item | Amount |
|---|---|
| Sale price | $45,000 |
| Tax (21% × 45,000) | (9,450) |
| Working capital recovered | 18,000 |
| Terminal cash flow | $53,550 |
Year 9 total = 205,400 + 53,550 = $258,950.
IRR and NPV (HP 10BII+)
[shift] [C ALL],1 [shift] [P/YR]646000 [+/-] [CFj]231776 [CFj],5 [shift] [Nj]205400 [CFj],3 [shift] [Nj](years 6-8)258950 [CFj](year 9)15 [I/YR],[shift] [NPV]→ 437,722.03[shift] [IRR/YR]→ 32.58
Answer: IRR is about 32.58% and NPV at 15% is about $437,722, so the equipment is a good investment.
Mistakes to avoid
- Adding the $30,000 consultant fee or the $50,000 training to the outlay.
- Keeping the $125,600 depreciation in years 6-9, which overstates cash flow.
- Entering 9 years of $231,776; only the first 5 years carry the tax shield.
More Capital Budgeting problems
- Lopez Industries projects A and B: MIRR compared with NPVModified internal rate of return for two mutually exclusive projects, compounding inflows at the required return, and a check of whether MIRR agrees with NPV.
- Neagle Corporation imposes a payback cutoff of 2.5 years: payback vs. NPVApplies a payback cutoff to two projects, then computes each project's NPV and shows where payback and NPV disagree, including the mutually exclusive choice.
- Project requiring construction expenses through year 2: IRR and NPVIRR and NPV for a project with three years of construction outflows before eight years of inflows, using grouped cash flows on the HP 10BII+.
- Consider the following cash flows that switch signs: IRR or NPV at 11%Non-conventional cash flows that change sign several times: computes the IRR, explains why IRR can be unreliable here, and confirms the decision with NPV and MIRR.
- Nonlinear Dynamics, Inc. must decide between two game projects: EAAChooses between two mutually exclusive projects with different lives and different risk-adjusted rates by converting each NPV into an equivalent annual annuity.
- Suppose your firm is choosing between two exclusive projects: PI vs. NPVRanks two mutually exclusive projects of different size by profitability index and by NPV, then explains why the ratio and the dollar measure disagree.
Got a different wording of this problem?
Assignments vary by school and semester. Share the version you were given and we'll add it so other students can find this solution.
Studying Capital Budgeting for a class?
Accuity courses map to your actual syllabus — video lessons, exam-style practice, and walkthroughs for the problems you're assigned.