Training software that eliminates $3,400 of yearly costs: NPV at 10.8%
Business FinanceCapital Budgeting
The problem
For $6,500, Accuity can buy training software that eliminates $3,400 a year of other training costs for the next 10 years. Use a discount rate of 10.8%.
- What is the net present value (NPV) of the software?
An Accuity original. We write our own version of each problem and solve it from scratch, so you learn the method rather than copying an answer.
Video solution
Covers the full step-by-step solution below, start to finish.

Solved by
Jake Glidden, CPA, MSA
Founder of Accuity
Jake started Accuity while studying accounting at UCF and has worked with hundreds of students in introductory and upper-level accounting classes. Accuity solutions are checked against the textbook before they're published.
Certified Public Accountant (CPA) · B.S.B.A. in Accounting, UCF · M.S. in Accounting, UCF
More about Accuity →Step-by-step solution
The same steps the video works through, written out.
This question tests net present value (NPV) for an investment that produces equal annual savings. Each avoided $3,400 training cost is a cash inflow, so the savings form a ten-year ordinary annuity.
The rule
NPV = PV of savings − cost = $3,400 × PVIFA(10.8%, 10) − $6,500
Accept when NPV > 0.
Step 1: Annuity factor
PVIFA(10.8%, 10) = [1 − (1.108)^−10] ÷ 0.108
(1.108)^−10 = 0.35859
PVIFA = (1 − 0.35859) ÷ 0.108 = 5.93895
Step 2: Present value of the savings
PV = $3,400 × 5.93895 = $20,192.43
Step 3: NPV
NPV = $20,192.43 − $6,500 = $13,692.43
HP 10BII+ keystrokes
Option 1 (TVM keys):
1 [shift] [P/YR],10 [N],10.8 [I/YR],3400 [PMT],0 [FV][PV]→ −20,192.43- Subtract the cost: 20,192.43 − 6,500 = 13,692.43
Option 2 (cash flow keys): 6500 [+/-] [CFj], 3400 [CFj] 10 [shift] [Nj], 10.8 [I/YR], [shift] [NPV] → 13,692.43
| Item | Value |
|---|---|
| Annual savings | $3,400 |
| PVIFA(10.8%, 10) | 5.93895 |
| PV of savings | $20,192.43 |
| Cost | ($6,500.00) |
| NPV | $13,692.43 |
Answer: the NPV is about $13,692.43.
What it means
The software creates about $13,692 of value in today's dollars beyond what it costs, so Accuity should buy it. A large positive NPV like this also implies a high IRR and a profitability index well above 1 (here $20,192.43 ÷ $6,500 = 3.11).
Mistakes to avoid
- Stopping at $20,192.43. That is the PV of the savings; NPV subtracts the $6,500.
- Summing the savings without discounting ($34,000 − $6,500 = $27,500), which ignores the time value of money.
- Keying 10.8% as 10 or 11. Small rate changes move a ten-year annuity noticeably.
More Capital Budgeting problems
- Lopez Industries projects A and B: MIRR compared with NPVModified internal rate of return for two mutually exclusive projects, compounding inflows at the required return, and a check of whether MIRR agrees with NPV.
- Neagle Corporation imposes a payback cutoff of 2.5 years: payback vs. NPVApplies a payback cutoff to two projects, then computes each project's NPV and shows where payback and NPV disagree, including the mutually exclusive choice.
- Project requiring construction expenses through year 2: IRR and NPVIRR and NPV for a project with three years of construction outflows before eight years of inflows, using grouped cash flows on the HP 10BII+.
- Consider the following cash flows that switch signs: IRR or NPV at 11%Non-conventional cash flows that change sign several times: computes the IRR, explains why IRR can be unreliable here, and confirms the decision with NPV and MIRR.
- Nonlinear Dynamics, Inc. must decide between two game projects: EAAChooses between two mutually exclusive projects with different lives and different risk-adjusted rates by converting each NPV into an equivalent annual annuity.
- Suppose your firm is choosing between two exclusive projects: PI vs. NPVRanks two mutually exclusive projects of different size by profitability index and by NPV, then explains why the ratio and the dollar measure disagree.
Got a different wording of this problem?
Assignments vary by school and semester. Share the version you were given and we'll add it so other students can find this solution.
Studying Capital Budgeting for a class?
Accuity courses map to your actual syllabus — video lessons, exam-style practice, and walkthroughs for the problems you're assigned.