Two mutually exclusive projects each costing $115,000: larger IRR or NPV

Business FinanceCapital Budgeting

The question

Each of two mutually exclusive projects involves an investment of $120,000. The firm's required rate of return is 11%. Use this information for the next 2 questions. The estimated cash flows are as follows:

YearProject A Cash FlowProject B Cash Flow
170,00010,000
240,00020,000
330,00030,000
410,00050,000
510,00090,000

Which of the following statements best describes projects A and B?

a. Project A has a larger IRR than project B.
b. Project A has a larger NPV than project B.
c. Project B has a larger IRR than project A.
d. Both (b) and (c) are correct.
e. None of the above are correct.

Below is the Accuity problem: the same method with different numbers. We solve ours, so work through it and you'll know how to solve yours.

The Accuity problem

Accuity must choose one of two mutually exclusive projects. Each requires an investment of $115,000 today, and Accuity's required rate of return is 10%. The expected cash flows are:

YearProject A Cash FlowProject B Cash Flow
165,0009,000
238,00018,000
328,00028,000
48,00045,000
58,00085,000
  1. Which statement best describes Projects A and B?

a) Project A's IRR is higher than Project B's.
b) Project A's NPV is higher than Project B's.
c) Project B's IRR is higher than Project A's.
d) Both (b) and (c) are correct.
e) None of the above is correct.

An Accuity original. We write our own version of each problem and solve it from scratch, so you learn the method rather than copying an answer.

Video solution

Covers the full step-by-step solution below, start to finish.

Jake Glidden, CPA, MSA

Solved by

Jake Glidden, CPA, MSA

Founder of Accuity

Jake started Accuity while studying accounting at UCF and has worked with hundreds of students in introductory and upper-level accounting classes. Accuity solutions are checked against the textbook before they're published.

Certified Public Accountant (CPA) · B.S.B.A. in Accounting, UCF · M.S. in Accounting, UCF

More about Accuity →

Step-by-step solution

The same steps the video works through, written out.

This question tests whether you can compute NPV and IRR for two projects and read which one leads on each measure. Both projects cost the same $115,000, but their cash flows arrive at very different times.

Step 1: Present value of each project's inflows at 10%

YearA cash flowPV at 10%B cash flowPV at 10%
165,00059,090.919,0008,181.82
238,00031,404.9618,00014,876.03
328,00021,036.8128,00021,036.81
48,0005,464.1145,00030,735.61
58,0004,967.3785,00052,778.31
Total121,964.16127,608.58

Step 2: NPV and IRR

HP 10BII+ for Project A: 115000 [+/-] [CFj], 65000 [CFj], 38000 [CFj], 28000 [CFj], 8000 [CFj] 2 [shift] [Nj], 10 [I/YR], [shift] [NPV], then [shift] [IRR/YR]. Repeat for Project B.

MeasureProject AProject B
PV of inflows at 10%$121,964.16$127,608.58
NPV at 10%$6,964.16$12,608.58
IRR13.49%13.05%

Step 3: Test each choice

  • (a) A's IRR is higher: 13.49% > 13.05%. True.
  • (b) A's NPV is higher: $6,964 < $12,609. False.
  • (c) B's IRR is higher: false (see a).
  • (d) needs (b) and (c) to be true. False.
  • (e) false, because (a) is true.

Answer: (a) Project A's IRR is higher than Project B's.

Why the measures split

Project A gets most of its money back in years 1 and 2, and IRR rewards fast payback. Project B's big inflows come in years 4 and 5. At a modest 10% discount rate those late dollars still carry a lot of value, so B has the higher NPV. The two NPV profiles cross at about 12.62%: below that rate B has the higher NPV, above it A does.

More Capital Budgeting problems

Got a different wording of this problem?

Assignments vary by school and semester. Share the version you were given and we'll add it so other students can find this solution.

Studying Capital Budgeting for a class?

Accuity courses map to your actual syllabus — video lessons, exam-style practice, and walkthroughs for the problems you're assigned.

Ace your accounting classes.

Textbook questions are for reference. We show a textbook's question only so you can find the problem you were assigned. We don't solve textbook questions: every solution and video on this site works through our own Accuity problem, written to teach the same method with different numbers.

Educational use. Accuity problems are original teaching material — we write our own version of each problem and solve it on video so you learn the method. Don't submit our work as your own; that violates your school's academic integrity policy. If you believe content here infringes your rights, file a DMCA notice.